Westside Waterproofing Update

Our waterproofing project is moving along nicely. The contractors have moved to the section over awning, so naturally we have routed foot traffic through the indoor pool door during the day, and arranged parking lot three rows back to avoid splashing of water, as well as paint. This is where the process takes a bit of time due to areas of the building that are identified as needing to be chipped away, treated, then concrete re-applied for painting. We are trying an additive to the paint this year that could help with the staining from water running down the building from corridors. Weather permitting this section should be completed within the next two weeks.

Thanks for the understanding, and cooperation,

Atalaya Towers Management