Water proofing / Parking Lot drain System

Submitted by atalaya on Sun, 02/10/2019 - 18:51


Our water proofing of the eastside of the building is complete, and it looks great. Due to the schedule of waterproofing the eastside we are finding very minor issues that bump up cost. We realize it's it bit of an inconvenience, but it's needed due to the exposure that side gets from weather. All caulking around sliders have been checked, and any issues were addressed by applying fresh caulk. We should be good for three more years. That is the schedule for this side.


Our parking lot change order appears to have been a good one. Instead of drain box with large grate at the entry to lobby and at the spa/indoor pool entry from parking lot we opted for two trench drains which span the entire area under the awning, and the entire window system at the spa. The intent is to enable as much water as possible in multiple areas to drain, therefore creating much less ponding and puddles. Weather was not our friend, so it looks like total completion, which includes patching, re-sealing and stripping may not happen until maybe April.

Posted in:
comments powered by Disqus