Submitted by atalaya on Sat, 11/10/2018 - 11:02


Our projects have begun for the fall after being postponed by hurricanes we were able to continue on with our water proofing of the building. We are hopeful to be completed with the 2-3 stacks within the next week or so weather permitting.


Our building drain project is scheduled to begin November 12th. This will involve some parking spaces closed off for a couple of days at a time. There will be machinery along with temporary walk-ways to and from the front of the building, also digging along the outdoor pool fence. After the construction stage of the project is complete the entire parking lot is scheduled to be re-sealed. This portion will require the entire lot to be emptied and moved to the lot across the street. Again, these projects are worked on when weather permits. The anticipated time for this to be completed is after thanksgiving.